Projects

VERTEX served as the surety’s construction consultant for the Patrick Henry High School project. The cost of the project was approximately $40 million which consisted of an entire site modernization (or renovation) of the existing grounds and a new theater building. VERTEX was retained close to the end of the project and assisted the surety and contractor with closing out the project. VERTEX’s scope of services included analyzing the cost expended and cost to complete, as well as analyzing the subcontractor cost and ultimately, helping to resolve payment bond claims. The project received a notice of completion on July 13, 2017. After completion, VERTEX assisted with the review of the contractor’s affirmative claims.

To learn more about VERTEX’s Surety Claims Consulting services or to speak with a Construction Expert, call 888.298.5162 or submit an inquiry