Find an expert

Learn More

Find the VERTEX expert perfect for your project.

See All Experts
News

Boston University Center for Computing and Data Sciences Milestone

December 7, 2020

On Saturday December 5, 2020, the Construction Team for the new Boston University Center for Computing & Data Sciences achieved a significant milestone. A massive amount of concrete was placed in a 5’ thick mat for the tower base, a key component in the transition to vertical construction activities.

Some interesting facts regarding the placement include:

•   4,500 cubic yards concrete

•   Delivered to site by 450 concrete trucks

•   Placed over 900 tons of steel reinforcing

•   Over 20 hours of continuous placement involving 3 pump trucks and 600 hours of workforce labor

•   Utilizing resources from the region’s 2 major concrete suppliers

•   Among the largest continuous concrete placements in City of Boston 

•   Embodied carbon concrete mix reduced over 700 tons of CO2 equivalent from being emitted to the atmosphere

This article was originally published by Compass which is now part of The Vertex Companies, LLC.

Back to Insights