SERVICES

VERTEX has Experts that Talk the Talk and Walk the Walk.

Unlike others, VERTEX provides forensic consulting alongside traditional AEC services which allows for a 360 degree view of your project.

VERTEX Services

Experts

Need an expert for your case?

Our forensics experts work alongside AEC specialists which enhances our skills and bolsters the credibility of our expert consultants.

Find an Expert

Portfolio

VERTEX delivers innovative solutions on complex projects globally.

Since 1995, VERTEX has completed over 90,000 projects.

View Portfolio

INSIGHTS

VERTEX believes in a Lifetime of Learning philosophy.

Stay current with our industry experts as they share their insights and knowledge on the built environment.

View Insights

Grow Your Career

Join Our Team

VERTEX is looking for talented individuals to join a highly technical team of forensic consultants, design engineers, construction managers, and environmental scientists.

Learn More

Contact Us

Have a question or want to speak with a technical professional?

VERTEX is a multi-discipline firm with global coverage. Our international network of resources enables us to provide multi-national clients with the most qualified local professionals who understand the culture, language, and regulatory framework.

Call Us: 888.298.5162

Call Us

Call us at 888.298.5162.

Articles

New York City’s L Train Repairs – Part 1: Recovering from a Natural Disaster

May 1, 2019

The Aftermath of Hurricane Sandy

In 2012, Hurricane Sandy hit the East Coast with a fury and cost New York City over $19B in damage. [1] Now, nearly seven years later, necessary repairs, including infrastructure rehabilitation, continue in response to the storm’s massive impact. While multiple subway systems in New York City have undergone repairs, there remains significant work to be performed.

L Train Tunnel Repair Plan

Following the storm, New York City began making plans to shut down the L Train from Bedford Avenue in Brooklyn, to Eighth Avenue in Manhattan, for a period of 15 to 18 months. The lengthy closure would be necessary to repair damage caused by the saltwater flood that corroded cabling and other electrical and track equipment.

The work required careful consideration and planning. The City would need to find transportation alternatives for the 400,000 daily commuters who rely on this major thoroughfare and reassure business owners who dreaded the economic implications of a lengthy shutdown. [2] Especially challenging: while some parts of the line could be repaired in less time, one tunnel — through which 225,000 passengers travel daily — would have to be closed for the entire period.

In 2017, after four long years of planning, feasibility studies, community proposals [3], and stakeholder outreach, the finalized repair plan was announced.

Then, just a few months before the planned start of work, despite all the planning, and amid declining real estate prices and lower rents in areas serviced by the line [4], New York Governor Andrew Cuomo announced that the original repair plan for the tunnel would be reimagined, and the shutdown averted entirely.

In this multi-part series, we will review several topics that tie-in to this story, including construction projects and stakeholders and the rise of Fiber-Reinforced Polymers.

The Best Laid Plans…?

The original repair plan called for the demolition and reconstruction of “approximately 60,000 linear feet of duct banks, 14,400 linear feet of track and track bed, 270,000 linear feet of cable ducts and associated cables, and 7,000 linear feet of concrete lining,” [5] as well as upgrading resiliency measures to protect the tunnel from future storms. The Metropolitan Transit Authority (MTA) depicted the planned scope of repairs in the graphic below:

Source: Metropolitan Transit Authority (MTA)

The repair work was awarded to a joint venture of Judlau Contracting, Inc. and TC Electric for a contract value of $477M, with a $17M incentive for completing the planned 18-months of repairs in 15 months.

Without warning, on January 3, 2019, following a walkthrough with engineering experts and just four months before the start of the work, Governor Cuomo announced that a shutdown would not be necessary and a new recommendation for the work was presented: [6]

Source: L Train Coalition

The New York Times generated a simplified representation of these changes: [7]

Original Plan

Source: NY Times

New Plan

Source: NY Times

Planning for the Future

Now, with the shutdown apparently averted and a new repair methodology to be implemented, New Yorkers hope that, unlike the tunnel itself, the plan holds water.

What happened here shines a light on how projects are planned and delivered, the factors that are weighed and parties impacted when a project is developed, and the technological advancements which make repairs like these possible. Future posts will explore the circumstances and outcomes that surround this project and the lessons learned.

To learn more about VERTEX’s Forensic Consulting and Engineering Design services or to speak with an Expert, call 888.298.5162 or submit an inquiry.

Series: New York City’s L Train Repairs

New York City’s L Train Repairs – Part 1: Recovering from a Natural DisasterPart 1
New York City’s L Train Repairs – Part 2: Construction Projects and StakeholdersPart 2 New York City’s L Train Repairs – Part 3: The Rise of Fiber-Reinforced PolymersPart 3
Back to Insights