SERVICES

VERTEX has Experts that Talk the Talk and Walk the Walk.

Unlike others, VERTEX provides forensic consulting alongside traditional AEC services which allows for a 360 degree view of your project.

VERTEX Services

Portfolio

VERTEX delivers innovative solutions on complex projects globally.

Since 1995, VERTEX has completed over 90,000 projects.

View Portfolio

INSIGHTS

VERTEX believes in a Lifetime of Learning philosophy.

Stay current with our industry experts as they share their insights and knowledge on the built environment.

View Insights

Grow Your Career

Join Our Team

VERTEX is looking for talented individuals to join a highly technical team of forensic consultants, design engineers, construction managers, and environmental scientists.

Learn More

Contact Us

Have a question or want to speak with a technical professional?

VERTEX is a multi-discipline firm with global coverage. Our international network of resources enables us to provide multi-national clients with the most qualified local professionals who understand the culture, language, and regulatory framework.

Call Us: 888.298.5162

Call Us

Call us at 888.298.5162.

Articles

When to Use the Total Cost Approach in Construction Claims

July 12, 2018

What is the Total Cost Approach?

One method used to price a construction claim is the total cost approach, which determines the value of the disputed work by subtracting the claimant’s bid prices from the actual performance costs. In this method, a comparison is made using project financials or other performance indicators such as actual vs. bid labor-hours. Successfully applying the total cost method in pricing construction claims requires meeting certain criteria.

As mentioned before, the total cost method compares actual costs with bid prices. The total cost method makes the dubious representation that everything the claimant did was flawless and every dollar above its bid is the result of the defendant’s actions. One variation, the modified total cost approach, is similar but makes adjustments to account for certain issues such as,

  • cost overruns due to contractor-caused problems
  • bid errors
  • change orders, and
  • another event unrelated to the actions of the owner.

Using the modified total cost results in calculating a net cost overrun and therefore, adds credibility to the claim by addressing both the imprecision and causation issues that arise from using the total cost method.

When Can I use the Total Cost Method?

The use of total cost or modified total cost method is predicated on satisfying a set of criteria, often referred to as the four-part test. To pass the four-part test, the contractor must demonstrate the following:

  1. The nature of the claim makes it impossible for the damages to be quantified in any other manner;
  2. The contractor’s actual costs are reasonable;
  3. The contractor’s bid estimate was reasonable; and
  4. The contractor is not responsible for the added costs.

Satisfying the above-referenced criteria is difficult and so both the total cost and modified total cost methods are viewed with skepticism. In cases where a project suffered from a multitude of significant disruptions, the total cost approach might be justified because the contractor’s entire performance is significantly different from what was expected. Examples include projects with

  • excessive and significant change orders
  • excessive design issues
  • work unique in nature or significantly different than the original contract work.

Is the Total Cost Method Right for My Situation?

Although using methods involving the maintenance of separated cost records for any impacted scope of work is recommended in claim quantification, the total cost approach may still be a viable alternative. In instances where keeping cost records separate was not possible, e.g. it was impractical to itemize increased direct costs, or when the cost has not been recorded separately, this method can be effective.

Ultimately, the total cost approach is most effective in achieving an equitable adjustment for construction disputes involving extra work claims, especially for complex types of construction claims. However, this method of claim pricing should be used with caution and an in-depth understanding of not only its capabilities but also its limitations.

To learn more about VERTEX’s Construction Claims Consulting services or to speak with a Construction Expert, call 888.298.5162 or submit an inquiry.

Back to Insights